Getting the keys to a brand-new home is a big moment. After months (sometimes years) of waiting, it's tempting to rush through the final steps and just move in. But the weeks right before and after closing are when a new-home buyer has the most leverage to get things fixed. If you're closing on a new build in Northwest Brampton, Mount Pleasant or Caledon this winter, I want you to go into that stretch prepared.
This guide covers the pre-delivery inspection (PDI), what to look for, and the Tarion warranty forms you'll want on your calendar for the first year. It's general information. For questions about your specific purchase agreement, talk to your real estate lawyer.
What the Pre-Delivery Inspection Is
Before you take possession, every Ontario builder must walk you through the home floor by floor. Tarion calls this the Pre-Delivery Inspection. During the walk-through, the builder should explain how to run the home's systems, like heating, ventilation, plumbing, electrical and air conditioning, and record anything that is incomplete, damaged, missing, inaccessible or not working on the builder's PDI Form.
That form matters. Tarion describes it as the official record of the home's condition before you move in. If there's a disagreement later about whether a scratch, chip or missing item was there before you arrived, the PDI Form is the evidence. At the same visit you'll review the Certificate of Completion and Possession, which shows your home's Tarion enrolment number and the date of possession. That date is when your warranty clock starts.
You or someone you choose must attend. Tarion says there's no restriction on who your designate can be, but if they'll sign for you, give the builder written authority using Tarion's Appointment of Designate form.
What to Check During the Walk-Through
Bring a copy of your purchase agreement, your phone for photos, and a little patience. Some things I'd look at:
- Finishes inside: chipped or cracked tiles, scratched countertops or mirrors, dents in walls, damaged flooring, and cabinet doors that don't line up.
- Doors and windows: do they open, close and lock properly? Are window screens installed?
- Outside: brickwork and siding, the driveway, grading and landscaping.
- What you paid for: compare finishes, colours and upgrades against your agreement. Tarion notes that items you had the right to select usually can't be substituted without your written consent, and other specified items can only be replaced with ones of equal or greater quality. Note any substitution on the form.
- Systems: make sure you understand how to operate the furnace, ventilation and water shut-offs. Tarion warns that not using a home's systems properly can affect your warranty coverage.
A winter note: snow, frozen ground and early darkness can make it impossible to check the driveway, grading, landscaping or parts of the exterior. Tarion's advice is simple: if you can't assess something, write that on the form. Don't let "we'll look at it in spring" go unrecorded.
Review the finished PDI Form carefully before you sign, and keep your copy somewhere safe.
Your First-Year Warranty Forms and Deadlines
The PDI isn't a warranty claim. Anything that isn't fixed by move-in, or that you discover afterwards, goes on Tarion's warranty forms, which you submit through Tarion's online MyHome portal. According to Tarion's claim forms and timelines page:
- Initial Form: you can start adding items the day after possession, and it's automatically submitted on day 41.
- Mid-Year Form: opens on day 42 and is automatically submitted on day 183.
- Year-End Form: opens on day 183 and is automatically submitted on day 365. This is your final chance to report items under the one-year warranty, and only one Year-End Form is accepted.
- Second-Year Form: can be submitted any time in the second year.
- Major Structural Defect Form: any time after year two, up to seven years from possession.
Tarion also asks that you tell your builder about issues and give them a chance to fix things before you bring a claim to Tarion. I'd suggest setting calendar reminders for each deadline the day you get your keys.
What the Warranty Covers, in Plain Terms
Tarion's coverage overview breaks the statutory warranty into three periods, all starting on the date of possession:
- One year: work and materials free of defects, Ontario Building Code compliance, the home being fit to live in, and protection against unauthorized substitutions.
- Two years: water coming through the basement or foundation walls, defects that let water into the building envelope, problems with exterior cladding like brick or siding, defects in the electrical, plumbing and heating systems, and Building Code violations affecting health and safety.
- Seven years: major structural defects, such as failure of a load-bearing element.
If you're buying a condo, remember the common elements (lobbies, hallways, garage) aren't part of your unit's PDI. Report problems there to the condo board.
Common Mistakes I See
- Rushing the PDI or treating it as a formality.
- Not taking photos of damage at the walk-through or on move-in day.
- Assuming the builder will remember a verbal promise. Get it in writing, by email if nothing else.
- Missing the Year-End Form deadline.
- Signing for items you couldn't actually inspect because of weather or access.
Helpful Resources
- Tarion: The Pre-Delivery Inspection
- Tarion: Claim forms and timelines
- Tarion: Warranty coverage after you close
- HCRA Ontario Builder Directory
- Law Society of Ontario: Finding a lawyer
Closing on a New Home Soon?
A new build is a big investment, and a little preparation at the PDI can save a lot of back-and-forth later. I'm happy to walk you through what to expect, help you prepare a checklist for your builder visit, and talk through timelines with you. Learn more on my New Home Construction Consultation page, or book a consultation and let's get you ready for closing day.